Hydroland: an Interview About the Vernon Dam’s Cultural Impacts

A well-crafted video project put together by two Brattleboro Union High School  (BUHS) students – Forest Zabriskie and Mason Redfield – for a recent class assignment.

To gather varied perspectives on the utilization of the Connecticut River – specifically the circa 1909 Vernon dam at the Great Bend in Sokwakik – they interviewed Matthew Cole, Community Relations for Great River Hydro (dam owner and operator); Kathy Urffer, River Steward for the Connecticut River Conservancy; and yours truly, for an Abenaki cultural viewpoint.

There are many ways to be in the world…

Advertisements

Great River Hydro’s FERC-Filed Notes from the 3/8/18 Study Results Summary

Cover letter:

Great River Hydro, LLC (“Great River Hydro”) is the owner and licensee of the Wilder Hydroelectric Project (FERC No. 1892), the Bellows Falls Hydroelectric Project (FERC No. 1855), and the Vernon Hydroelectric Project (FERC No. 1904). The current licenses for these projects each expire on April 30, 2019. On October 31, 2012, TransCanada initiated the Integrated Licensing Process by filing with the Federal Energy Regulatory Commission (“FERC” or “Commission”) its Notice of Intent to seek new licenses for each project, along with a separate Pre-Application Document for each project.

With this filing, Great River Hydro submits its March 8, 2018 Updated Study Results Meeting Summary for the three projects, as required by 18 C.F.R. §5.15(c)(3) and the Commission’s current Process Plan and Schedule (dated February 15, 2018). The meeting for the Updated Study Reports filed between May 1, 2017 and February 9, 2018 was held at Great River Hydro’s Renewable Operations Center in Wilder, Vermont, with teleconference and call-in capability for participants who could not attend in person.

Below is a comment excerpt:

ILP Schedule – Brandon Cherry reviewed the Revised Process Plan and Schedule FERC issued on February 15, 2018, noting that GRH is required to file a progress report on May 15, 2018 and every 90 days thereafter until studies 9 and 24 are completed. The progress report is to include the status of study 33 – Cultural and Historic Resources Study.

Study 33 – Cultural and Historic Resources Study – Rich Holschuh concurred that this study is still open and indicated that while the draft TCP includes timetables for consultation, no consultation has taken place. John Ragonese disagreed that no consultation had occurred, citing several meetings with native American tribal leaders and informational resources but recognized the present open status of the study. He said the Programmatic Agreement (PA) and Historical Properties Management Plan (HPMP) are in development and will be shared for comment and review. The PA is a signed agreement among affected parties that usually includes SHPO’s, licensee and federal tribe(s). GRH suggests that no federal tribe is affected by this PA, but local tribes are and therefore should be included. The PA will reference the HPMP which includes details of how properties will be managed.

VT Public Service Department Backs Sale of 13 TransCanada Hydro Dams

TransCanada Bellows Falls Station Randy Holhut

key state agency has signed off on the sale of 13 hydroelectric stations to a Boston company. The Vermont Department of Public Service – whose job is to represent the public interest in energy matters – has approved a deal pledging to support Great River Hydro’s proposed purchase of TransCanada’s dams on the Connecticut and Deerfield rivers.

Jim Porter, director of the department’s Public Advocacy Division, said the agreement came after a thorough review of the sale and after negotiation with Great River. “We did conclude the sale facilitated the general good of the state,” Porter said. “The sale will not affect Vermont jobs, and Great River Hydro demonstrated it is capable of managing these assets.”

Read the full story by Mike Faher at VTDigger.org.